The ideal Quartzline PU cast floor in five days
You achieve a modern, sleek PU cast floor in five days with Quartzline Deco UV. Day 1, you start by repairing the floor if necessary. If necessary, use Alpha SL Underlayment 2-20mm for this. Then you use Primer PU BHH to prime the floor. This layer also ensures good adhesion to the subfloor.
On day 2, apply SL-PU Scratchcoat. This layer is for filling pores and leveling the subfloor and suitable as an undercoat for the screed.
Day 3 apply your own leveling screed SL-PU UV NF. This is an aliphatic two-component, solvent- free, pigmented polyurethane floor with tough elastic properties. After this, let the floor dry for 12 hours.
Day 4 is reserved for applying the top coat of Quartzline Coating PU SG NF Satin Gloss. This is a two-component, water-based, transparent silk gloss polyurethane-based topcoat.
After this, allow the floor to cure for 48 hours and you have applied another top floor